SERVICE (cont.)
Test Procedures:
1. Disconnect the brewer from the power source;
2. Remove the wires from the (+) and (-) terminals on
the rectifier to be tested.
3. With a voltmeter check the voltage across the (+)
and (-) terminals on the rectifier. Connect the
brewer to the power source. The indication must
be 24 volts dc.
4. Disconnect the brewer from the power source.
If voltage is present as described, the rectifier is
operating properly.
If voltage is not present as described, refer to the
brewer wiring diagrams and check the brewer wiring
harness.
+
A
C
A
C
FIG. 27 SERVER DETECT RECTIFIER TERMINALS
P1381
YEL to Interface Circuit Board J2-2 (Left)
ORA to Interface Circuit Board J2-1 (Right)
BLU/BLK to Transformer #7
BLK to Interface Circuit Board
J2-5 & J2-6
BLU/BLK to Circuit Breaker
RECTIFIERS
FIG. 26 RECTIFIERS
P2232
Location:
One pair of rectifiers are located inside the base
housing on the right side of the base plate just in front
of the transformers. Another pair of rectifiers are
located in the hood housing just in front of the Water
Tank Assy.
Removal and Replacement:
1 Disconnect the wires from the rectifier.
2. Remove the #6-32 truss head screw securing the
rectifier to the brew base plate.
3. Remove the rectifier and discard.
4. Install new rectifier on base plate and secure with
a #6-32 truss head screw.
5. Refer to Fig. 27 & 28 when reconnecting the wires.
32248 100500
+
A
C
A
C
FIG. 28 FUNNEL LOCK RECTIFIER TERMINALS
P1381
RED to Funnel Lock Solenoid
BRN/BLK to DBC J1-15 & Indicator (Left)
RED/BLK to DBC J1-14 & Indicator (Right)
BLK to Funnel Lock Solenoid
Whi to Indicator Light & DBC J1-14