ICB Training Manual
20
Step 6: Rebuild the bypass valve(s)
Remove the hose clamps that secure the tubing to the valve
Remove the two 11/32 nuts that hold the solenoid bracket to the machine
Gently remove the tubing from the valve body
Using a 1/4 nut driver, remove the four screws and separate the valve assembly
Replace plunger, spring, and rubber seat using the rebuild kit BUNN P/N: 11517.0008
Clean any mineral build-up from the valve
Reassembly is the opposite of disassembly
Step 7: Check the funnel lock solenoid(s) for correct operation
Step 8: Replace the seat cup in the hot water faucet (annually)
Unscrew the faucet bonnet from the assembly
Remove the old faucet seat cup
Install the new seat cup BUNN P/N: 02766.0000
Reassembly is the opposite of disassembly
Step 9:Visuallyexaminethepowercordforanydamage
Step 10:Visuallyexaminethewatersupplyforanyleaks
Step 11:Calibratesprayheadowrateandbypassowrate